Expanded Learning Opportunities Program (ELOP) | Elk Grove, CA

The Expanded Learning Opportunities Program (ELOP) involved relocating and refurbishing six modular buildings across different campuses, requiring new utilities, accessibility upgrades, and added amenities such as a garden. FLINT oversaw the project and ensured strict adherence to the schedule, completing utility work within two weeks at three year-round schools and allowing classes to continue uninterrupted. Most refurbishments were carried out off-site, reducing campus disruption. Overall, FLINT completed all campus upgrades and building relocations within 15 weeks, maintaining a tight timeline throughout the project.

Project Value

$8.1 million

Square Footage

5760

Delivery

Lease-Leaseback

Owner

Elk Grove Unified School District

Architect

PRIMEBuisness